LAKE OZARK, Mo. — Work continues to resurface the Bagnell Dam bridge, as the Missouri Department of Transportation attempts to lengthen the life of a bridge that Missouri drivers have been crossing for 90 years.
But how old is too old, for a bridge? MoDOT Area Engineer Bob Lynch says MoDot typically has a pretty good answer to that question. Engineers inspect Missouri’s bridges every year or two, depending on the condition — Lynch says the Bagnell Dam bridge will likely be on a two-year cycle once it reopens to traffic. As time goes on, that will likely become a yearly inspection. Those assessments will give engineers a good sense of how much life the old bridge has left in it.
The structural inspections allow engineers to identify areas of concern too, like they did in 2020 with the Lake’s iconic swinging bridge, which was abruptly closed to all traffic when engineers found a major weakness in one of the bridge’s anchor points.
And while Bagnell Dam’s bridge is a far cry from the remarkable, rickety swinging bridges, Lynch said no bridge lasts forever, and MoDOT expects this one has a decade or two left. “The bridge is 90 years old,” he said. “So we are trying to get another 15 to 20 years of life out of it.”
It’s important to clarify these projections only apply to the bridge on top of the dam, not the dam structure itself. “It’s very much a bridge attached to the dam,” Lynch said, explaining the driving surface (deck) rests on girders held up by piers that sit on top of the dam. Bagnell Dam itself underwent an extensive reinforcement project by Ameren in 2017; that project blasted away and replaced old concrete from the dam's face, and installed structural tension rods into the dam, anchored into the bedrock. It cost Ameren approximately $52 million.
The current bridge work that has closed the dam bridge to traffic since September 2021 is costing MoDOT an estimated $1.6 million. " The purpose of this project is to repair the bridge deck, expansion joints and barrier walls and to replace the bridge driving surface and repair the adjacent sidewalk," MoDOT said on the project webpage. See progress updates and more information here.
When the bridge reopens—hopefully this spring, MoDOT Central District Communications Manager Adam Pulley says—there will be a weight limit of 18 tons, and Lynch said that’s part of the effort to lengthen the bridge’s lifespan. But when asked about what a new bridge across the dam might look like, Lynch said it’s too early to know.
“Everybody’s initial assumption is that it would go on top of the dam again… but really you don’t know that either,” he said, noting it’s too early to begin making any firm plans for a replacement. “We don’t start doing any design concepts this early,” Lynch explained. “Maybe five years out we’d start looking at it.”
As for the cost to replace the dam, Lynch points to the new Hurricane Deck Bridge, which opened in late 2013. It cost $30 million to build. “That’s what you’re looking at,” he said. “30 to 50 million dollars, to build something.”
Related Stories
It’s a common experience for anyone who drives much in Lake Ozark. You’re headed across the …
LAKE OF THE OZARKS, Mo. — When will Bagnell Dam reopen to traffic? It’s the question nearly …
LAKE OF THE OZARKS, Mo. — Explosions boomed through the frigid, midday air, announcing the d…
Bagnell Dam Reinforcement Project:
For its 85th birthday, Bagnell Dam is having some work done.
LAKE OZARK, Mo. — Aged concrete is being blasted off the face of Bagnell Dam by water jets, …
LAKE OZARK — Construction crews have poured the final yards of concrete and are completing f…