SUNRISE BEACH, Mo. – Upgrades to a wastewater treatment system taken over by the village for the Phase 1 sewer project are nearing completion, according to Schultz and Summers Engineering Branch Manager Jim Fisher.
“I am happy to report we are moving full steam ahead on the sewer project, Fisher said.
“We are in the process of perpetuating the anti-degradation report to the Department of Natural Resources. We have made an application to the Department of Geology and Land Survey, and the Department of Conservation for the required reports. Our deadline to get our applications to DNR is June 20, to meet their funding requirements, and that won’t be an issue. We are also in the process of revising our contracts to meet the new budgetary amounts and the city’s project specifics, and the attorney’s comments on the contract. We should get the draft back from the attorney in the next few days and we plan to give a copy to the city.”
The Sunrise Beach Board of Trustees last month unanimously approved plans for the Phase 1 sewer system, choosing to rehabilitate an existing treatment plant on Dave Buehler’s land, located at the Sunrise RV Park on Forsen Park Road near the Hurricane Deck Bridge, and extend a line north to Lake Road 5-39 using a lift station.
Schultz and Summers Engineering representatives Jim Burton and Jim Fisher recommended the treatment plant rehabilitation project after investigating several options, including pumping affluent to existing treatment plants run by the City of Laurie, the Gravois Arm Sewer District and TT Sewer Company.
Fisher also met with City Planner Roger Corbin last week to review sewer plans submitted by engineers working on the proposed Tax Increment Financing project that Associated Grocers has proposed at the corner of Highways 5 and F.
Discussion continues about connecting the grocer’s sewer project with Phase 1 of the village’s central line.“This would be mutually beneficial for all parties involved,” Fisher said.
Water Project Cleanup
Maagi Construction has begun the cleanup of construction debris from the city water project, Sunrise Beach Public Works Director Barry Campbell told the Board of Trustees last week.
According to Campbell, Maagi started working on the north end of Phase 2 toward the Sunrise Beach Community Center, then plans to move to Bear Bottom Resort, the far north end of the line, before completing the punch list to the south.
Campbell said the village has been receiving complaints about the clean-up work not getting done.
“I was told the contractors would be back before the end of April to do the clean up and that is what I have been telling customers. They did not come back until today,” said Campbell.
Several business parking lots and drives are still torn up and they are getting busy and want their drives fixed, according to Campbell.
Dangerous buildings and debris
The board discussed a dilapidated property on Lake Road 5-35 at the old Cardinal Resort.
“There are buildings that are falling down that could be a danger to children. I can’t say anything about everything else sitting out in their yard,” Mooney said.
The board approved a request to have attorney Greg Williams send a letter to the property owners asking them to clean up the property.
Police department
The Sunrise Beach Police Department received 160 calls for service in April. The department issued 60 traffic warnings and 54 citations.
Merchant and liquor licenses
The city issued a merchant license to Williams Bobcat, Sunrise Maintenance and Laurie Motors II. The board also issued liquor license renewals for Shrimp Daddy’s and Sunrise Cantina.
Mooney reported two new computers are being installed at City Hall. Mooney approved a bid from Lake Computer Repair to purchase two computers, one monitor, and peripheral devices for $1,895. The bid included Windows 7, transferring all records and the installation of an anti-virus program.
Finance
The board approved an ordinance adopting an annual budget for the fiscal year beginning Sunday, April 1, 2012 and ending Sunday, March 31, 2013, and approving funds pursuant thereto for the water system.
The total city revenues in April were $37,540.47; expenses were $26,628.13, leaving a net income of $10,812.34.
The next meeting of the Sunrise Beach Board of Trustees is scheduled for 6 p.m., Monday, June 11 at City Hall.