More than a dozen years ago, the City of Lake Ozark got itself in deep trouble. A major sewage spill landed the city's public works administrator with federal probation, and the city was slapped with a consent judgment requiring it to clean up its act.

It's taken 13 years for the city to comply with the requirements set forward in that consent judgment, and during all that time, the city has been ineligible to receive federal and state grant money -- costing the city as much as a million dollars a year, according to Mayor Dennis Newberry.

With the completion of the Twin Oaks lift station, the city has now satisfied the consent judgment requirements, however.

City officials were notified June 24 that a Satisfaction of Judgment had been filed with the Missouri Department of Natural Resources announcing that DNR would be closing its enforcement case. 

“The past 13 years have required a lot of difficult work on the part of our staff, citizens and board of aldermen,” City Administrator Dave Van Dee said. “This resolution finally puts to bed the dark cloud that was hanging over Lake Ozark for so long, and we can now begin looking to the future.”

What Happened

It all started in early September 2007 when the DNR was alerted by an individual that raw sewage was flowing into the lake. The DNR discovered that a lift station on Horseshoe Bend Parkway had failed and was allowing between 10,000 and 15,000 gallons of raw sewage to flow into the Lake. 

The DNR notified the city of the bypass, and the city responded and stopped the flow but failed to conduct clean up or provide written notification of the bypass.

Fallout

A year after the spill was reported, the public works director – who had been fired as a direct result of the mishap – pled guilty to failing to report the discharge of pollutants into the lake and was sentenced in U.S. District Court to three years of probation. The court also ordered the fired employee to pay a $5,000 fine.

In a separate but related case, the City of Lake Ozark plead guilty to repeatedly discharging raw, untreated sewage from several sewage collection stations directly into the Lake of the Ozarks. The discharges were from sewage overflows resulting from faulty equipment. The city was fined $50,000 by the DNR and $30,000 by the Environmental Protection Agency.

As part of the judgment, the city agreed to upgrade and maintain its wastewater treatment system and to report any and all bypasses from its treatment system and lift stations as required by the state.

Cleaning Up Its Act

The city has between 300 and 400 grinder pumps and lift stations that serve the community. All of those had to be upgraded or replaced to meet a subsequent court order. 

Then-Mayor Johnny Franzeskos and the board of aldermen hired McClure Engineering to design and upgrade the system at a cost of about $3 million. Of that total, the city borrowed $200,000, which was repaid in full and ultimately impacted the city’s sewer budget.

“It was an awesome and sometimes arduous task,” Van Dee said. “The DNR and McClure Engineering worked together to guide us through the process. Two mayors, multiple aldermen and our staff were involved over the years and their quick action on various ordinances and work orders helped expedite the projects.”

Over the following decade, the city worked to make the mandated improvements, doing some of the work internally. Improvements include:

•Rehabilitation of nine lift stations

•Replaced hundreds of grinder pumps and control panels

•Cleaned and CCTV (Closed Circuit Television) inspected the gravity flow sewer system

•Re-lined and sealed several lift station wet wells and manholes

•Installed remote monitors which alert Public Works staff via text message of any failure within the system

Final Piece

The final piece of the puzzle was the upgrade of Twin Oaks Lift Station on Twin Oaks Drive, which was completed to the satisfaction of city officials and the DNR only recently. The city blames the delay of its completion—about two years—on their inability to obtain the needed easements from lift station neighbors. Eventually, the DNR, McClure Engineering and the public works staff designed an alternate way to access the lift station.

“It’s taken quite a while, but now we have a wastewater system in place that has the capacity to handle our anticipated growth,” Van Dee noted.


 

LakeExpo covered another major sewage infraction in 2020, when our exposé revealed the Sunrise Beach Public Works Director had been deliberately discharging sewage down a hillside, through a lakefront neighborhood, into the Lake. Read more below...